A quarry which had been dormant for six years has brought back into productivity with support from high performance washing plant supplied by
The CDE system has been configured to a bespoke layout, bringing together standard modular relocatable units to create a solution specific to the quarry’s exact requirements.
The plant features a S2910 static feed conveyor; AggMax 252SR Logwasher assembly, and a Prograde P2-42 twin-deck washing screen, as well as a H1565 transfer conveyor and Evowash 151 triple cyclone sand unit.
Other elements include six C1565 stockpilers; a ProGrade rinsing deck and sizing screen, and a Trackstack 8042 TSL sand stockpiling unit.
APS, the specialist washing arm of the Finlay Group of companies, has introduced each of the components so they all work in tune with each other, to deliver maximum performance.
The plant has also been designed to comply with the stringent guidelines for the site, in accordance with its location next to Paxton Pits Nature Reserve, which is a site of special scientific interest (SSSI).
This includes measuring up to specific height and noise restrictions, as well as being coated with a Moorlands Green colour, which is designed to blend in with the environment.
Now in operation for eight months, the plant is currently powering through 200tonnes/hour to produce a +75mm, a 75mm-40mm, a 40-20mm, 20-10mm and a 20-5mm product as and when required, as well as soft and sharp sand.
Aggregate Industries has a long-standing relationship with APS, which sells complete systems as well as contracting and hiring of processing equipment.
Duncan Hayden, assistant site manager at Little Paxton Quarry, said: “As a company we’ve been working with APS for around ten years and they always meet our needs.
“The whole experience has been very good and we’re extremely happy with the new plant.”
Aggregate Industries currently has four contracts nationwide with APS, and the plant at Little Paxton operates on a price per tonne basis.
John Dunne, managing director of APS, said: “It’s great that the quarry is back up and running and I’m happy to see how pleased Aggregate Industries is with its new washing system.”