An investigation has begun into a collision involving a passenger train and an aggregates train in county Leicestershire, England. The Rail Accident Investigation Branch (RAIB) said at around 10.27am on 14 February 2016, the 10.20am East Midlands Trains service from Leicester to York was in collision with a conveyor boom projecting from an aggregates train standing in Barrow-on-Soar sidings (some Network Rail documents refer to the sidings as Mountsorrel sidings).
March 1, 2016
East Midlands Trains passenger train involved in the collision
Image showing damage to the East Midlands Trains passenger train involved in the collision

An investigation has begun into a collision involving a passenger train and an aggregates train in county Leicestershire, England.

The Rail Accident Investigation Branch (RAIB) said at around 10.27am on 14 February 2016, the 10.20am East Midlands Trains service from Leicester to York was in collision with a conveyor boom projecting from an aggregates train standing in Barrow-on-Soar sidings (some Network Rail documents refer to the sidings as Mountsorrel sidings).

An RAIB statement said: ‘It [the passenger train] consisted of a seven car class 222 diesel multiple unit and struck the boom of the wagon, which was projecting over the line, at approximately 102 mph (163 km/h). The maximum speed allowed for this type of train at this location is 110 mph (176 km/h). The driver applied the emergency brake and the train stopped approximately 0.75 miles (1.21 km) from the point of impact.

‘The front coach of the train was damaged by the impact but did not derail. The unloading conveyor arm was also damaged and a member of staff, who had been working on the conveyor, was seriously injured and was taken to hospital by air ambulance. Nobody on the train was injured, but the driver was badly shaken.

‘After the accident, the train was moved at low speed to Loughborough station where the passengers were detrained to continue their journeys on other services.

‘The wagon involved in the accident was part of a train which had been loaded with aggregates ready for departure the following day. It was being prepared for service by the member of staff at the time of the accident.’

The RAIB said its investigation will examine the sequence of events leading up to and during the collision, the preparation and maintenance work that was being carried out on the wagon, the procedures which govern this work and any underlying management issues.’

Its investigation is independent of any investigation by the railway industry, the Office of Road and Rail (ORR) or the Health & Safety Executive.

The RAIB said it will publish its findings, including any safety recommendations at the conclusion of its investigation.