Installation of a new washing plant in Paekivitoodete Tehase's quarry in Estonia is helping to turn 50 years of waste into saleable aggregates
Paekivitoodete Tehase - which translates as Limestone Products - first opened its Vao quarry near Talin in Estonia in the 1950s to supply the local construction market with limestone aggregates. But until now equipment at the site was unable to process material with a high clay content and this 'waste' from 50 years of operation had been stockpiled on site.
Today this material is being reprocessed to add value to Paekivitoodete Tehase's extraction work at the Vao site. This change in practise has been made possible with the installation of a new washing plant at the site by Ireland-based CDE - the first of its kind in Estonia.
Since the company was founded it has developed a reputation for innovation, and this is something that the staff are very proud of. "We are seen as leaders in Estonia in relation to bringing new technologies and processes to the market," explained Paekivitoodete Tehase chairman Vladimir Libman. "The introduction of this CDE washing plant is a good example of how we approach business. This system has never been used before in Estonia and we are delighted to say that we are the first to use them." The CDE washing plant has been brought in specifically to deal with material which has been stockpiled as waste since the site began production. This material is a by-product of the crushing processes in the quarry and up until now, Paekivitoodete Tehase have not been able to find a system capable of processing it in a way that will produce commercially viable products in a cost effective manner.
Paekivitoodete Tehase first saw CDE's approach to this problem at last year's Hillhead and after a visit to another quarry in Ireland that is successfully using the equipment to process 'dirty' material, it ordered its own plant.
The Estonian plant begins with a 20tonne feed hopper, which in turn feeds the latest addition to the CDE product line, the AtroFeed, which is designed to provide water jet attrition to the clay bound materials. The material is then fed to a double deck rinsing screen from CDE's ProGrade range and the over 16mm material and 5-16mm material is stockpiled.
The under 5mm material is sent to a heavily customised dual sands plant from CDE's EvoWash range, where the 2-5mm grit is rinsed again and dewatered and the 0-2mm material is pumped to the second screen. The washed sand
(-63micron to 2mm) is stockpiled while the waste water and -63 micron material is sent to a CDE AquaCycle T08 thickener. This forces the sludge to settle and this is then pumped to settling ponds. The clean water is recycled back to the washing system, dramatically reducing the requirement for fresh water to feed the plant.
According to CDE it is the high level of customisation in this plant that has allowed Paekivitoodete Tehase to process this waste material into commercially viable products. "The evidence that an off the shelf product would not have been able to process this material comes in the fact that this material has been here for 50 years," explained CDE sales director Enda Ivanoff. "Only through a system built specifically to deal with the individual characteristics of this project were we able to solve the problem for Paekivitoodete Tehase."