Cemex has completed its nine month-long project to upgrade its ready mixed concrete facility in Grimaud, France. The €1.9million investment enables the plant to produce up to 80m3 of concrete per hour and has also improved the site’s recycling and environmental performance.
March 28, 2012
Read time: 1 min
643 Cemex has completed its nine month-long project to upgrade its ready mixed concrete facility in Grimaud, France. The €1.9million investment enables the plant to produce up to 80m3 of concrete per hour and has also improved the site’s recycling and environmental performance.