Russia’s Evraz Kachkanarsky Ore Mining and Processing Enterprise (Evraz KGOK, a subsidiary of
The project started in April 2013 with investments amounting to RUB 17 million (€387,067.24), and the first phase featured delivering a heavy vehicle complex; a standby storage for crushed stone, and a shipment fiscal metering complex.
The weighting complex capacity was 240 trucks/day (with a weight limit of 100tonnes) in August 2013.
The second phase will feature construction of a sifting complex (for 10-20mm and 20-40mm stone fractions) and launching crushed stone production for the Sverdlovsk region's construction sector (Urals).